Turn “it feels Amber” into rules everyone applies the same way. Set your thresholds, copy the Green / Amber / Red definitions, and test them on a task before you adopt them.
1. Set your thresholds
2. Your criteria
Green (all of these)
- Forecast finish is no more than 2 working days after the baseline finish.
- The owner has confirmed the task is on track.
Amber (any of these)
- Forecast finish is 3 to 10 working days after the baseline finish.
- The owner can't say yet whether it's on track (no date confirmed).
Red (any of these)
- Forecast finish is more than 10 working days after the baseline finish.
- A committed milestone, customer or regulatory date will be missed, however many days.
- It has been Amber for 2 reviews in a row without a recovery date.
- Measure slip against the saved baseline, not last week's date, so a slow drift still shows.
- The worst dimension sets the color: one Red condition makes the task Red.
- Every Red task needs an owner-proposed recovery date and plan by the next review.
- Status reflects the forecast, not effort or intent. A task can be Red with everyone working hard.
3. Test a task
Amber. Slip of 4 working days is more than 2.
Everything runs in your browser. Nothing is sent or saved.
Why write the criteria down
A RAG color is only useful if it means the same thing every week and to every reader. Written criteria stop two common failures: the “watermelon” status that is green on the outside and red inside, and the late surprise where a task jumps from Green straight to Red the week it's due. Agreeing the thresholds up front also takes the politics out of turning something Red.
Making the rules hold up
- Measure against the baseline. Keep the original finish date and compare the current forecast to it. The schedule slip calculator does this for a whole list of tasks.
- Ask the owner for the forecast. Criteria are only as good as the dates behind them. A short, specific question works best; the status request email generator writes one.
- Let “hard to say” be Amber. Uncertainty is a risk worth showing, and people answer more honestly when it's an allowed answer.
- Re-baseline deliberately. When scope changes, re-baseline with sign-off rather than quietly moving the goalposts. See when to re-baseline a project schedule.
Questions
What are RAG status criteria?
Written rules that decide whether a task or project is reported Red, Amber or Green. Without them, color is a mood: one person's Amber is another's Green. With them, anyone looking at the same dates reaches the same color.
What thresholds should I use?
Base them on how much float your schedule has and how much a late date costs. A common starting point is Green up to a couple of working days late, Amber up to about two weeks, and Red beyond that or whenever a committed milestone is at risk. Agree them with the team and sponsor before the first report, not after a task turns Red.
Should slip be measured against the baseline or last week's date?
The baseline. Measured against last week, a task that slips two days every week stays Green forever. Against the baseline, the drift adds up and shows.
Is anything I enter saved?
No. The rules are built in your browser and nothing is sent to PingCadence or anyone else.