What you see after a check-in

PingCadence emails each task owner a short check-in from your own Outlook or Gmail, after you approve the batch. This is what comes back to you: who is on track, who sent new dates, and the report you forward upward.

Sample plan. The project, people and dates are made up. Nothing on this page is saved or sent, and the buttons are shown as they look in the app but do nothing here.

Excel upload · 10 tasks

Customer portal launch

Check-in sent Mon, Nov 16, 9:00 AM · answers due Wed, Nov 18 · shown as of Nov 19, 2026

On track

4

Hard to say

1

Not on track

2

No response

2

Step 1 of 3 · Review

Needs your decision 2

When an owner says a task is not on track, they give a new start and end (or a duration) and a reason. The new dates wait here until you decide. Nothing is written to your plan or tracker without your click.

  • Payment provider integration

    Ben Ortiz proposed new dates

    +11 days vs baseline
    Baseline
    Oct 26, 2026 → Nov 13, 2026
    Current
    Oct 26, 2026 → Nov 13, 2026
    Proposed
    Oct 26, 2026 → Nov 24, 2026

    “The provider's test environment was down Nov 3 to Nov 6. Refunds still need two days of work and a day of testing with them.”

  • Help center articles

    Fatima Rahman proposed new dates

    +7 days vs baseline
    Baseline
    Nov 9, 2026 → Nov 25, 2026
    Current
    Nov 9, 2026 → Nov 25, 2026
    Proposed
    Nov 9, 2026 → Dec 2, 2026

    “The settings screens are still changing. I can write the last six articles in a week once they're frozen.”

This sample plan came from a file, so the first button accepts the dates in PingCadence. With a connected tracker such as monday.com, Asana or Jira, it reads “Apply to …” and writes the dates back for you (on Pro).

Step 2 of 3 · Every answer

What each owner said

9 tasks were in this check-in. Owners answer from a private link with no account to create. You can add up to three questions of your own; this one asked “Anything we should raise at Thursday's steering meeting?”

Payment provider integration

Ben Ortiz · ends Nov 13, 2026

“The provider's test environment was down Nov 3 to Nov 6. Refunds still need two days of work and a day of testing with them.”

Not on track

Help center articles

Fatima Rahman · ends Nov 25, 2026

“The settings screens are still changing. I can write the last six articles in a week once they're frozen.”

Not on track

Onboarding screens

Chen Wei · ends Nov 20, 2026

On track

Account settings page

Dana Kim · ends Nov 25, 2026

On track

QA test plan

Ana Lopez · ends Nov 20, 2026

“Depends on whether we get a second tester. I'll know Friday.”

Steering meeting: The second tester request.

Hard to say

Data migration dry run

Eli Novak · ends Nov 13, 2026

No response

Load testing

Eli Novak · ends Nov 27, 2026

No response

Security review

Hassan Ali · ends Nov 24, 2026

Steering meeting: No.

On track

Launch checklist

Grace Liu · ends Nov 30, 2026

On track

Still waiting on Eli Novak (Data migration dry run, Load testing). On Pro, PingCadence reminds them on the schedule you set.

Step 3 of 3 · Report

The slip report

Built from the answers and your decisions, every task measured against the baseline you imported. Download it as a PDF or CSV, or print it, on Pro.

Tasks

10

Response rate

78%

Later than baseline

1

Awaiting a PM decision

2

Needs attention (3)

  • Payment provider integration · Ben Ortiz

    Baseline Oct 26, 2026 → Nov 13, 2026; now Oct 26, 2026 → Nov 13, 2026 · proposed Oct 26, 2026 → Nov 24, 2026 · awaiting PM decision

  • Help center articles · Fatima Rahman

    Baseline Nov 9, 2026 → Nov 25, 2026; now Nov 9, 2026 → Nov 25, 2026 · proposed Nov 9, 2026 → Dec 2, 2026 · awaiting PM decision

  • Data migration dry run · Eli Novak

    Baseline Nov 12, 2026 → Nov 13, 2026; now Nov 12, 2026 → Nov 13, 2026 · past its end date, no answer

All tasks

  • Design sign-off

    Done

    Ana Lopez

    Baseline
    Oct 19, 2026 → Oct 30, 2026
    Current
    Oct 19, 2026 → Oct 30, 2026
  • Payment provider integration

    Not on track

    Ben Ortiz

    Baseline
    Oct 26, 2026 → Nov 13, 2026
    Current
    Oct 26, 2026 → Nov 13, 2026
    Proposed
    Oct 26, 2026 → Nov 24, 2026

    awaiting PM decision

  • Help center articles

    Not on track

    Fatima Rahman

    Baseline
    Nov 9, 2026 → Nov 25, 2026
    Current
    Nov 9, 2026 → Nov 25, 2026
    Proposed
    Nov 9, 2026 → Dec 2, 2026

    awaiting PM decision

  • Onboarding screens

    On track

    Chen Wei

    Baseline
    Nov 2, 2026 → Nov 20, 2026
    Current
    Nov 2, 2026 → Nov 20, 2026
  • Account settings page

    On track

    Dana Kim

    Baseline
    Nov 2, 2026 → Nov 20, 2026
    Current
    Nov 2, 2026 → Nov 25, 2026 (+5 d)

    new dates applied

  • QA test plan

    Hard to say

    Ana Lopez

    Baseline
    Nov 9, 2026 → Nov 20, 2026
    Current
    Nov 9, 2026 → Nov 20, 2026
  • Data migration dry run

    No response

    Eli Novak

    Baseline
    Nov 12, 2026 → Nov 13, 2026
    Current
    Nov 12, 2026 → Nov 13, 2026
  • Load testing

    No response

    Eli Novak

    Baseline
    Nov 16, 2026 → Nov 27, 2026
    Current
    Nov 16, 2026 → Nov 27, 2026
  • Security review

    On track

    Hassan Ali

    Baseline
    Nov 16, 2026 → Nov 24, 2026
    Current
    Nov 16, 2026 → Nov 24, 2026
  • Launch checklist

    On track

    Grace Liu

    Baseline
    Nov 23, 2026 → Nov 30, 2026
    Current
    Nov 23, 2026 → Nov 30, 2026

“Account settings page” was already moved: Dana Kim sent a new end date last week and it was new dates applied, so it shows +5 days against the baseline. Statuses use the same words everywhere: On track, Hard to say, Not on track, No response.